Contractor said he warned of Davenport building collapse, told workers 'Get away. You’re going to die'
About three months before the partial collapse of a downtown Davenport apartment building — and again just two days before — a masonry company owner said he predicted it was
qctimes.com
Five people are unaccounted for.
About three months before the partial collapse of a downtown Davenport apartment building — and again just two days before — a masonry company owner said he predicted it was coming.
City officials say at least five people are unaccounted for after the partial collapse Sunday evening at 324 Main St. Families of two men fear they remain under the rubble of the fallen west side of the six-story building.
No new updates came from the city Wednesday on rescue operations or a potential timeline for demolishing the building, which remains standing after city officials said Monday that "demolition is expected to commence" on Tuesday.
However, the city released hundreds of pages of documents Wednesday close to 6 p.m. detailing structural engineering reports, notices of violations, orders to vacate some apartments and resident complaints over the past three years.
Ryan Shaffer, co-owner of R. A. Masonry, was working nearby at 112 W. 3rd St., the former Antonella’s Pizza, in February. While on the job, he said, he was approached by Andrew Wold, the owner of the building where the collapse occurred.
The building owner approached a contractor to get a quote for work needed on the building. Apparently the owner rejected the quote and tried to get the contractor to do a cheaper job, which the contractor refused because it would not be safe for his workers.
Shaffer said Wold asked him to supply a quote for work on the nearby apartment building. When he did, he said, the bid was rejected because it was too high.
“He wanted to cut the cost by cutting out the shoring and supporting of the building," Shaffer said.
Shoring is done to prop up a building when the structure is deemed unsafe, Shaffer explained. The bid for that work alone came in at about $50,000.
“I said, ‘If we don’t do it this way exactly, I’m not putting my guys in there. Somebody is going to die,’ ” he said.
According to Shaffer, Wold then shopped around for someone who would do the work for an acceptable price. City records reflect this.
On Feb. 22, the city of Davenport issued a permit for, “structural masonry repairs to west elevation as specified in engineer's report.”
According to the permit, the job came at a cost of nearly $40,000. The contractor listed is Bi-State Masonry.
The chief building inspector (who has since resigned) declared the building secure.
City inspection records show a final inspection was done on March 1 by Trishna Pradhan, the chief building official for Davenport. The building passed inspection, and the work was being completed in line with the structural engineer's report.
The exterior finish of the building needed to match the historic fabric of the rest of the building. Pradhan wrote that the contractor was aware and the owner was being informed.
In the next sentence, it was noted Bi-State was off the job as of March 1 because the “owner did not agree to their change order for installing brick outside.”
Pradhan continued, saying repair work was on hold but shoring was in place and, “site is secure. Owner has not submitted new timeline for work to commence.”
Work then appears to have resumed, and it passed three more city inspections on April 12, April 21, and May 1. In the last one, the inspector noted “repair work has been completed per Engineer’s Report.”
A separate permit for brickwork was filed on Wednesday, May 24. City records indicate the job consisted of replacing 100 feet of brick on the exterior of the building, per city code.
The permit says the work came at a cost of $3,000. The contractor on the job is listed as “owner.”
Shaffer said, in his opinion, the work described would account for only one-third of what needed to be done. Saturday, one day before the collapse, he drove by and saw a pile of bricks on the ground.
“(Wold) was calling us and asking for I-beams and stuff to support it. I looked at it and was like, ‘There’s no saving it at this point,’” he said.
Friday, two days before the building collapsed, Shaffer said he went to the apartment building and told workers, “Get away. You’re going to die.”
Sunday, at 3:30 p.m., less than two hours before it collapsed, he warned workers at the site of 324 Main St. that they needed to leave.
“We were here working all day," he said, referring to his work at the former Antonella's location. "Literally, we were just waiting for the building to drop."
Social media users this week questioned why the status of that final inspection on the city’s website changed. On Monday, as viewed through an internet archived site, the city’s site listed the May 25 inspection as “passed.” Now, that same inspection status is “failed.”
City officials attributed this to a system “glitch” that the city is working to correct. The site “shows any inspection marked as ‘Incomplete’ with a fail/error message” Chief Strategy Officer Sarah Ott wrote in an email and included screenshots of the internal systems.
“This is not a failed inspection but an incomplete inspection since no re-inspection could be completed,” she wrote.
Select Structural Engineering, of Bettendorf, was hired by Wold to advise on work being done on the building in the past year. City officials said the engineering firm had determined that the building was structurally sound for tenants to stay in while the exterior work was being done.
There were other documents from one of the contractors indicating numerous problems with the building, and the other contractor said that he was standing and watching just waiting for it to collapse. It's too bad they couldn't issue an evacuation order to get everyone out before it collapsed.
There was also a discrepancy on the city's website, first showing the building passed inspection, and then that it failed - which city officials blamed on a glitch.
And why would the building inspector say it's safe when another local contractor said that it was so close to collapse that he had to warn workers to get out of there and stay away because "you're going to die"?
Something is totally messed up about this whole situation.